6.2.2 Site
selection and basic layout
As adequate head and flow are necessary requirements for
hydro power generation, site selection is conditioned
by the existence of both requirements. Before a site is
selected, a preliminary assessment study should include
definition of power potential, estimation of power output,
identification of physical works needed, identification
of critical issues (environmental and social constraints),
and a preliminary study of economic feasibility.
Source:
Ref 7.7
Figure
6.2 High head small hydropower scheme
SHP schemes
can be high-head or low-head depending on the geographical
characteristics of the available site. In general high-head
sites are less expensive to develop than low-head sites,
because for the same power output the flow through the
turbine and required hydraulic structures will be smaller.
In a river with a steep gradient over part of its course,
the level difference can be utilised by diverting all
or part of the flow and returning it to the river once
it has passed through the turbine. The water can be brought
from the intake directly to the turbine through a pressure
pipe.
A cheaper alternative is the one shown in figure 6.2.
The scheme comprises a dam or a weir, a river intake,
and an almost?level open canal running along the side
of a river valley ending in a forebay (local open basin),
from where a pressure pipe conducts the water down to
the turbine in the powerhouse. If the topographical or
geotechnical characteristics of the ground are unfavourable
the open canal may not be the best solution. A low pressure
pipe, the "penstock", may provide a more economic
solution in such circumstances.
In low-head
schemes two configurations are possible. One uses a diversion
weir with a layout very similar to the above, although
the canal is usually short and the penstock short or non-existent
(figure 6.3). The other involves a dam with an integral
intake and powerhouse.

Source Ref 6.1
Figure 6.3 Low head small hydropower configuration
Another
possibility is to install a power plant on an existing
dam built for multiple purposes (flow control, irrigation,
etc.). Water enters the turbine through a penstock constructed
as an integral part of the dam structure or, if the dam
is not too high, through a syphon intake (figure 6.4).

Source
Ref 6.1
Figure
6.4 Power plant scheme on an existing conventional dam
In the syphon solution the penstock runs over the dam
before sloping down to the turbine, which can be located
either on top of the dam or on the downstream side. Although
the head in most syphon installations varies from 1.8
to 11 m, there are a few examples with heads as large
as 30 m.