5.5 COST
AND ECONOMICS
5.5.1 Construction
The cost
of constructing a wind turbine generator is very important
because this almost entirely determines the cost of the
electricity generated. As may be expected, the cost per
rated kW output decreases with increasing size. A typical
breakdown for a wind farm installation is shown below:
| Manufacture of complete wind turbine |
63%
|
| Site works |
29%
|
| Other capital outlay |
8%
|
Manufacturing
cost has been coming down steadily over the last 15 years
as a result of improved technology, volume production
and larger unit size. The turbine cost per rated kW depends
on both the turbine size and the wind speed at the site,
but is typically in the range 500-700 €/kW. A total
wind farm installation cost may be as low as 800 €/kW.
5.5.2 Capacity
credit
The economic viability of wind power depends particularly
upon whether the investment can be offset by a reduced
requirement for conventional power station capacity in
the utility system. Such a system obviously cannot meet
its power demand reliably with wind power alone, because
the wind does not always blow. But a large system comprising
a range of generators is not the same as a remote wind/diesel
unit in which the wind turbine merely saves the cost of
diesel fuel, since demand and supply are continuously
fluctuating (see also Section 5.2.4.5.1 above about the
separate problem of control and wind prediction). The
question is then how to determine the proportion of wind
power which can contribute to the useful capacity of the
system without loss of reliability, or its capacity credit.
Because of wind speed fluctuation, the annual electrical
energy output of a wind farm is typically about 30% of
the maximum possible if its rated power could be delivered
continuously. This ratio is known as the load factor or
capacity factor of the wind farm, and depends mainly on
the the site conditions but also on the type of turbine.
All types of generator (fossil fuel, nuclear etc) have
load factors, which although they may be higher than 30%
are always less than 100%, and depend on the possibility
of failure as well as the need for maintenance. The requirement
of the overall power system is that a complete loss of
power should be very unlikely, or have a low enough annual
probability such as 1%. It can be shown that for low levels
of penetration of wind power into the grid, the capacity
credit of wind energy is simply the installed capacity
multiplied by the load factor. However as the level of
wind penetration rises (e.g. to 15% of maximum annual
demand), the capacity credit falls off and might be halved
in this case. Denmark has exceeded this amount of wind
power without apparent difficulty, but after that the
country with the highest wind power penetration to date
is Germany with less than 5%, so Europe still has a long
way to go before this becomes a problem.
5.5.3 Unit
cost
The price
of wind generated electricity depends on the plant installation
cost and the cost of finance, both spread over the energy
generation expected during the lifetime of the plant,
with a quite small addition for operating cost (e.g. 15
€/yr per rated kW). The price per kWh therefore depends
on the average wind speed at the site, the load factor
and the cost of finance, of which the third tends to be
more unpredictable than the first two. At a good site,
a price to the client or distributing company of 3.5 c€/kWh
is possible, which is highly competitive with the true
costs of conventional power (i.e. if all decommissioning
costs are realistically included and historic subsidies
discounted). It is largely for this reason that Europe
is investing in Wind power so successfully.